Successful trials of RSS-GM-195!
From September 28 to October 5, 2020 at the Yuzhno-Priobskoye field drilling of a directional section with a horizontal end using the domestic rotary steerable system RSS-GM-195 developed by “BURINTEKH”, Ltd was successfully performed!
The total interval length was 1920 m (from 1560 to 3480 m). The well section was constructed without deviations from the design profile. The final inclination of the drilling interval was 85,75 degrees. RSS-GM-195 is the first rotary steerable system to drill specified interval.
RSS-GM-195 has no analogues in the world; more than 90% consists of Russian components. This system during the construction of a directional section with a horizontal end, according to the results of the seventh field trials at Gazpromneft-Khantos site, has shown its reliability and ease of operation.
Rotary steerable system RSS-GM development is supported by the Industrial Development Fund (IDF).
-
With the support of the Russian Export Center “BURINTEKH”, Ltd participated in African Energy Week - one of Africa’s key industry forums - held in Cape Town in October 2026.More -
“BURINTEKH”, Ltd breaks into the Egyptian Market.
In late August a technical presentation took place in Cairo, hosted jointly with our Egyptian partner, Drexel Company. The event brought together representatives from the Egyptian General Petroleum Corporation (EGPC) and key operators in Egypt’s oil and gas sector.More